Sunday 5 July 2020

KADAPA ULTRA MEGA SOLAR PARK ANDHRA PRADESH, INDIA ๐Ÿ‡ฎ๐Ÿ‡ณ๐Ÿ‡ฎ๐Ÿ‡ณ

๐ŸŒžKADAPA ULTRA MEGA SOLAR PARK ANDHRA PRADESH, INDIA๐ŸŒž



KADAPA ULTRA MEGA SOLAR PARK is generally owned by andhra pradesh solar power corporation limited (APSPCL).For a certain time period due to corona virus /covid-19, the kadapa solar park is shut temporarily. the kadapa solar park makes use of FLAT PLATE PHOTO-VOLTAIC PANELS. The site resource of the solar park is 5.5-6.0 kWh/m2 per day. 

⚡The site area of the kadapa solar park is 5,927.76 acres(23.9888 km2). The total of 250MW of units is operational in kadapa solar park and 750MW of units is under construction. So, we could say that after the project completion a total of 1000MW of generating capacity can be expected from kadapa solar park. therefore, the total capacity of Kadapa solar park is 1000MW(MEGA WATT).In the earlier blog I have explained about pavagada solar park and Bhadla solar park, the total capacity of both are nearly 2050 MW and 1700MW respectively and when these two solar park are compared with the kadapa solar park the generating capacity is quite less and modification is required. 

๐ŸŒžINDIA'S SOLAR ENERGY CORPORATION OF INDIA (SECI) TENDERING 650MW FOR KADAPA SOLAR PARK ANDHRA PRADESH ๐ŸŒž

⚡The Solar Energy Corporation of India (SECI) has issued a request for selection (RfS) for 650MW of grid-connected solar PV projects at the Kadapa Solar Park in Andhra Pradesh.The capacity, which is split into 500MW open category and 150MW under Domestic Content Requirement (DCR) rules, comes under the National Solar Mission, phase II, batch IV.Last March, Indian state-owned utility NTPC also issued an RfS for solar developers to set up a 250MW solar PV project in the kadapa Solar Park. 


⚡Kadapa Ultra Mega Solar Park is a solar park spread over a total area of 5,927.76 acres (23.9888 km2) in the Mylavaram mandal of Kadapa District , Andhra Pradesh.The project is being implemented by the Andhra Pradesh Solar Power Corporation Private Limited (APSPCL), a joint venture of solar energy corporation of India (SECI), andhra pradesh power generation corporation and the New & Renewable Energy Development Corporation of Andhra Pradesh Ltd. 

⚡A 1,000 MW solar park at Kadapa was approved by the Union Government in August NTPC Limited invited bids from solar power developers to develop 250 MW capacity in March 2016 and 650 MW capacity in July 2016.


⚡The auction for 250 MW concluded on 11 April 2017. NTPC awarded the contract to French firm solairedirevt for a record-low tariff of INR 3.15 per kWh, beating the previous low of INR 3.29 per kWh awarded in auctions for the Rewa Solar Park on 10 February 2017.The price is the levellized tariff for 25 years. Although the Rewa contract was awarded at a cost of INR 2.97 per kWh, the levellized tariff over the contract's 25 year period amounts to INR 3.30 per kWh.The other bids received for the project (and the quoted prices) were Canadian Solar Energy (Rs 3.39), Greenko Energies (Rs 4.09), Azure Power (Rs 4.38), Mohoba Solar (Rs 4.54) and Mahindra Renewables (Rs 4.68). 

⚡In January 2017, SECI issued India's first grid-scale solar-plus-storage tender to install 5MW/2.5MWh battery energy storage systems to two separate solar projects of 50 MW each in the park.

⚡The project has been delayed due to Andhra Pradesh discoms refusing to purchase the power generated at the solar plant. Discoms argue that solar tariffs have dropped considerably since the auction for the Kadapa park took place and prefer to source power from other sources. 


⚡In February 2020, 250 MW capacity was commissioned by Solairedirect and the remaining 750 MW is under various stages of construction.

๐ŸŒžIn 24 October 2017 NTPC was searching for buyer for kadapa solar park


⚡Six months after it conducted a solar auction of 250 MW at the kadapa solar park in Andhra Pradesh , NTPC has still not been able to find a buyer for the power the project will produce, people aware of the matter said.

⚡All 250 MW at the April auction were won by SolaireDirect, a subsidiary of the French energy giant Engie, quoting a tariff of Rs 3.15 per kWh, which was a record low at the time.

⚡But so far Engie has not even received a Letter of Award (LoA) from NTPC confirming that it had been allotted the project, sources said. Usually, the power purchase agreement (PPA) with the winner of an auction is signed within a validity period of two months after the auction.But in this case, no PPA has yet been signed, and the validity period was recently extended for the third time – this time for a month – till mid-November, sources said.

⚡Neither Engie nor NTPC responded to queries about the delay as of press time Monday.

⚡Sources said the ministry of new and renewable energy (MNRE) is seized of the matter, more so because Engie is France’s biggest power utility, and France and India are key movers of International Solar Alliance (ISA). MNRE secretary Anand Kumar declined to comment on the development.The problem has arisen because Andhra pradesh discoms, which were expected to buy the power in the normal course, have declined to do so.

⚡Though Engie’s tariff, quoted in April was the lowest then, two more solar auctions conducted by Solar Corporation of India at the Bhadla Solar Park in Rajasthan in May saw the winning tariffs fall further, first to Rs 2.63 and then to Rs2.44 per kwH.


⚡As a ripple effect, Andhra Pradesh in July decided that solar power at Rs 3.15 per kWh was too high a tariff. Its nodal agency for renewable energy New and Renewable Energy Corporation of Andhra Pradesh (Nredcap) informed NTPC it was no longer interested in buying, but offered to waive transmission charges if NTPC got any other state to buy it. (ET, July 24)

⚡Sources revealed that NTPC has held discussions with nodal renewable energy agencies of several other states to buy the power.

⚡“States which have not yet embarked on a solar programme but need to fulfil their renewable purchase obligations (RPOs) could benefit from this project,” said one of the sources.

⚡But no decision has been reached yet. And NTPC has failed to finalise a PPA notwithstanding its reputation and the quality of power it guarantees.

⚡“Validity periods for signing PPAs have been extended by some states in the past, but rarely ever by NTPC,” said an industry insider. “Usually NTPC readily finds buyers. But the rapid and steep fall in solar tariffs seems to have unsettled the market.”

⚡Engie currently has around 325.6 MW of commissioned solar projects in India and is building another 140 MW project at the Bhadla Solar Park.

⚡During a visit to India in May this year, Engie CEO Isabelle Kocher had said her company intended to invest at least $1 billion in Indian solar projects over the next five years. (ET, May 31) But such hiccups could well lead to a rethink.

๐ŸŒžNTPC TENDER FOR 250MW IN ANDHRA PRADESH, NHPC 50MW EPC TENDER IN TAMIL NADU ๐ŸŒž

๐Ÿ’‍♂️NTPC = NATIONAL THERMAL POWER CORPORATION 
๐Ÿ’‍♂️NHPC = NATIONAL HYDRO-ELECTRIC POWER CORPORATION 


⚡India’s largest utility NTPC has invited bids for a single solar PV project of 250MW capacity to be set up at the Kadapa Solar Park in Andhra Pradesh under open category.

⚡The deadline for bid submissions is 7 December this year. The tender comes under the National Solar Mission (NSM) Phase II, Batch II, Tranch I.

⚡NTPC aims to build 10GW of solar in India under its own steam, but consultancy firm Bridge to India recently said that NTPC is struggling to finf off-takers for this capacity in an environment dominated by private sector firms that can bid low and very aggressively.


⚡This week Climate Bonds Initiative hailed NTPC's INR20 billion (US$299 million) Green bond as a model that should be replicated across fossil fuel firms across the world.

๐ŸŒžNHPC 50MW๐ŸŒž(NATIONAL HYDRO-ELECTRIC POWER CORPORATION) 

⚡In other news, Indian state-run power firm National Hydroelectric Power Corporation (NHPC) has issued a tender for EPC services to develop a 50MW grid-connected solar PV project located at Theni and Dindigul Districts in the State of Tamil Nadu along with O&M services for 10 years.

⚡The project is to be completed within nine months of the contract award. The deadline for bid submission is 24 November this year.

⚡In June NHPC announced plans to set up a 600MW floating solar photovoltaic project at the Koyna hydroelectric project in the Satara district of Maharashtra. The PV project will be combined with pumped hydro storage



No comments:

Post a Comment

If you have any doubts or clarification you need in my blog topics, I would ๐Ÿ’ฏ try to clear it in an efficient manner as possible. I will also accept your suggestions.

๐Ÿ’‍♂️ARTIFICIAL SUN CREATED BY CHINA ๐Ÿ‘ˆ

๐ŸŒž ARTIFICIAL SUN MADE BY CHINA ๐ŸŒž ☀️China successfully powered up its “artificial sun” nuclear fusion reactor for the first ti...