🔥On 27 November 2010 the Kaiga Atomic Power Station unit 4 of 220 MW capacity became operational.
🔥On 19 January 2011, unit 4 with 220 MW capacity was connected to the southern power grid at 01:56 hours. With this, the total capacity rose to 880 MW making it the third largest in India after TARAPUR (1400 MW) and RAWATBHATA (1180 MW). The unit, fueled by indigenous uranium, will supply electricity to karnataka , andhra pradesh, kerala, tamil nadu and Puducherry.
🔥In December 2018, it got the distinction of setting a world record of continuous operation among all nuclear power plants. As on December 10, 2018, KGS-1, which was synchronized to India's Southern grid on May 13, 2016, continues to operate for a record number of 962 days. Previous record of continuous operation was held by UNIT 8 of Heysham 2, which operated from February 18, 2014 to September 15, 2016 for a record number of 940 days.
🔥Two PHWR(PRESSURIZED HIGH WATER REACTOR) units each producing 700 MW have been planned for this location.As of February 2017 pre-project activities have begun for them and if everything goes as planned the first of the two will become critical around 2024-25.
🏭UNITS OPERATIONAL CHART LIST ON KAIGA NUCLEAR POWER PLANT 🏭
Unit | Type | Gross MW | Construction start | Operation start | Notes |
---|---|---|---|---|---|
Phase I | |||||
Kaiga 1 | PHWR | 220 | 1 September 1989 | 16 November 2000 | [9] |
Kaiga 2 | PHWR | 220 | 1 December 1989 | 16 March 2000 | [10] |
Phase II | |||||
Kaiga 3 | PHWR | 200 | 30 March 2002 | 6 May 2007 | [11] |
Kaiga 4 | PHWR | 220 | 10 May 2002 | 20 January 2011 | [12] |
Phase III (planned) | |||||
Kaiga 5 | IPHWR-700 | 700 | [13] | ||
Kaiga 6 | IPHWR-700 | 700 |
🔥The indigenously-developed 220 MW capacity Unit 4 of the Kaiga Atomic Power Station attained criticality at 8.07.22 am making India the sixth country in the world to have 20 or more nuclear power plants in operation.
🔥A nuclear reactor is said to have attained criticality when it is ready to maintain stability of the chain reaction indicating that the unit is has achieved a steady output of power.
🔥The Kaiga-4 was built a few years ago but was unable to start power production for want of fuel.
🔥India's exemption from the Nuclear Suppliers' Group guidelines in 2008 that facilitated its return to global nuclear trade made the access to fuel possible.
🔥The announcement of Kaiga-4 attaining criticality was made by Atomic Energy Commission Chairman Srikumar Banerjee in the presence of Nuclear Power Corporation of India Limited (NPCIL) Chairman-cum-Managing Director Shreyans Kumar Jain and a number of senior officials at the plant site.
🔥"I announce that Unit 4 has attained criticality," said Banerjee. He said that it would be the endevour of the department to ensure that the new unit is connected with the grid as early as possible which could be followed by commercial production of power.
🔥The Kaiga Unit 4 will now undergo a series of checks from the Atomic Energy Regulatory Board (AERB) before being synchronised with the grid. The commercial production will begin thereafter.
🔥The entire processes from criticality to commercial production takes about two months.
🔥Three units of 220 MW each are already generating electricity at the Kaiga nuclear station at about 60 per cent of their capacity.
🔥Kaiga is NPCIL's sixth nuclear power plant site.
🔥The third unit at Kaiga attained criticality in February 2007 in less than five years of first pouring of concrete. Kaiga 1 and 2 had attained criticality in 2000.
🔥Kaiga 4 has raised the installed capacity at the power station here to 880 MW, the third largest site of NPCIL after Tarapur and Rawatbhata.
🔥Presently, India produces 568 billion units of electricity and of that 23 per cent is from hydro-power, 64 per cent from thermal power, 10 per cent by non-conventional methods and only three per cent by the nuclear power.
🔎KAIGA NUCLEAR POWER PLANT is the 2nd best nuclear power plant in the whole world and it is successful in supplying electricity to karnataka, tamil nadu, andhra pradesh, Telangana, puducherry and kerala. Regarding this was mentioned in article published on 7 November 2018.
🔥The Kaiga Atomic Power Station in Uttara Kannada district of Karnataka has achieved a historic feat. The Unit 1 of the plant, run by the Nuclear Power Corporation of India Limited, has the best record of continuous operation among Pressurised Heavy Water Reactors (PHWR) and second among all nuclear power stations across the globe. The announcement was made by state-owned Bharat Heavy Electricals Limited(BHEL) which provided the hardware of steam turbine generator for the utility unit.
🔥BHEL, in a statement on Tuesday, said that the unit had been functional since May 13, 2016, and crossed the record of 894 days held by Pickering Nuclear Generating Station (PNGS) in Canada. The unit 1 is an indigenous PHWR and is also fuelled by domestic fuel. Earlier in June, the same unit had set a new record of operating for 766 days continuously, beating Unit 5 of Rajasthan Atomic Power Station (2014). Another 28 units have surpassed the mark of running continuously for one year.
🔥The Kaiga plant had started commercial operations in November 2000, after being commissioned in 1989 and currently supplies power not only to the state but also to neighbouring states of Telangana, Andhra Pradesh, Tamil Nadu, Kerala, and the Union Territory of Puducherry. In all, the plant set up 56 km away from Karwar, currently has four functional units generating 220 MW of power. 33% of the power generated is reserved for Karnataka.
🔥However, the expansion of the plant adding two more units has been opposed by a section of locals and environmentalists owing to environmental and immediate health concerns.
🔥In a study, the Tata Memorial Centre found that in the years 2010 to 2013, the number of cancer patients shot up by 300% in the vicinity of the plant. A compilation of data of 30 plants showed that while there were only 70-80 cancer patients in Karwar prior to 2010, the numbers increased to 316 during 2010-2013. The study was commissioned after the Nuclear Power Corporation of India and the state government gave in to the demands of a public pressure group to conduct population-based cancer registries.
🔎Indian designed nuclear reactor breaks the highest record for continuous operation. India’s 220-MW Kaiga 1 nuclear power plant, an indigenously designed pressurized heavy water reactor (PHWR), on Dec. 31 became a world record holder for running 962 unbroken days. The previous record for continuous operation was held by Heysham-2 Unit 8 in the UK, which ran 940 days before it was taken offline on Dec. 10.
🔥The state-owned Nuclear Power Corp. of India Ltd. (NPCIL) said the 1999-completed unit at the four-unit plant in Uttara Kannada district of Karnataka state continuously operated from May 13, 2016, until Dec. 31, 2018, when it was taken offline for inspection and maintenance. During that period, the unit generated about 5 billion units of electricity at a plant load factor of about 99.3%.
🔥India’s 220-MW Kaiga 1 nuclear power plant, an indigenously designed pressurized heavy water reactor (PHWR), on Dec. 31 became a world record holder for running 962 unbroken days. The previous record for continuous operation was held by Heysham-2 Unit 8 in the UK, which ran 940 days before it was taken offline on Dec. 10.
🔥The state-owned Nuclear Power Corp. of India Ltd. (NPCIL) said the 1999-completed unit at the four-unit plant in Uttara Kannada district of Karnataka state continuously operated from May 13, 2016, until DEC 31, 2018, when it was taken offline for inspection and maintenance. During that period, the unit generated about 5 billion units of electricity at a plant load factor of about 99.3%.
1. The 220-MW Kaiga 1 in Uttara Kannada district of India’s Karnataka state went offline on Dec. 31, 2018, after completing 962 days of continuous operation—a world record. Courtesy: India Department of Atomic Energy |
🔥Kaiga 2, 3, and 4 (which were completed between 2000 and 2012) are still running, and as of Jan. 1, Kaiga 2 had operated continuously for 661 days. NPCIL noted that along with Kaiga, several Indian nuclear reactors have achieved continuous operation of more than 365 days 28 times. Two other reactors, Rajasthan 3 and Rajasthan 5, have reportedly achieved continuous operating runs of 777 days and 765 days, respectively.
🔥The record unbroken run “demonstrates the pre-eminence of NPCIL in the design, construction, and operation of PHWRs with unprecedented levels of efficiency and safety,” NPCIL said in a statement. Specifically, the entity credited “a synergistic partnership forged between public sector enterprise and the industry partners in the private sector,” adding these have been “instrumental in gaining wide ranging experience and expertise and developing world class technology in this domain, which is now being fruitfully leveraged towards the expansion of the nuclear power programme of the country.” New Delhi–based state-owned engineering and manufacturing company Bharat Heavy Electricals Ltd. (BHEL), which equipped Kaiga 1 with its steam turbine generator set, said in a separate statement that the achievement showed India’s indigenous nuclear program had attained maturity.
🔥India currently operates 18 PHWRs, each rated at either 220 MW or 540 MW, for a total installed PHWR capacity of 4.5 GW. NPCIL, meanwhile, is building four 700-MW PHWRs, two at Kakrapar Atomic Power Station in Gujarat and two at Rajasthan Atomic Power Station. BHEL steam turbine generator sets are installed at 12 of India’s 18 operating PHWRs. BHEL noted it has been “a partner for over four decades in the development of the indigenous nuclear power program since its inception.”
🔥India’s nuclear power sector was conceived in 1948, shortly after independence, when it established its Atomic Energy Commission. In the beginning, the nuclear energy program was modest, owing largely to its lack of resources. The country has sparse uranium resources, but it holds 25% of the world’s total reserves of thorium (which is not fissile). In 1974, the country was excluded from the Nuclear Non-Proliferation Treaty for acquiring nuclear weapons capability, and during the next three decades in isolation, when it was viewed as a nuclear pariah, the country developed a three-stage nuclear program based on a closed-fuel cycle, where spent fuel of one stage is reprocessed to produce fuel for the next stage.
🔥The first step of the three-stage program involves building indigenously engineered PHWRs fueled by natural uranium (U). “Natural uranium contains only 0.7% of U-235, which undergoes fission to release energy (200 Mev/atom). The remaining 99.3% comprises U-238, which is not fissile, however, it is converted in the nuclear reactor to fissile element Plutonium-239 [Pu-239]. In the fission process, among other fission products, a small quantity of Pu-239 is formed by transmutation of U-238,” NPCIL explained. The country’s first 220-MW PHWR at Rajasthan 1, completed in 1973, was based on CANDU (Canada Deuterium Uranium) technology, but India relied on domestic designs for the others after Canadian assistance was withdrawn in 1974, even as the second Rajasthan unit was under construction. In 1981, it completed Rajasthan 2, and went on to complete Madras 1 and 2 between 1984 and 1986 using a standardized 220-MW PHWR design. Kaiga 1 and 2, and Rajasthan 3 and 4, which came online around 2000, incorporated improvements to the design.
🔥The nuclear program’s second stage comprises fast breeder reactors (FBRs), which are fueled by mixed oxide of U-238 and Pu-239, recovered by reprocessing of the spent fuel from the first stage. Once the program has established enough inventory of Pu-239, the fast reactors will use Thorium-232 to breed U-233, NPCIL said. The country currently has plans to build two prototype FBRs at Kalpakkam in Tamil Nadu, a site that already hosts a 500-MW fast breeder test reactor. In September 2018, the Department of Atomic Energy announced that the test reactor—which was originally expected to be commissioned in 2012 and has suffered several delays—is expected to achieve criticality in 2019. In the third stage, using wholly indigenous technology, the country will use advanced heavy-water reactors fueled with U-233 obtained from the irradiation of thorium in PHWRs and fast reactors.
🔎ACCORDING to the article that was published by deccan herald in 17 February 2017" The first 700 MWe nuclear power reactor at Kaiga is likely to produce commercial electricity only by the middle of the next decade, a top official has confirmed. “Pre-project activities have begun for Kaiga units 5 and 6 (two reactors of 700 MWe each). But even if everything goes according to plan, the first unit at Kaiga can become critical only around 2024-25,” Sekhar Basu, chairman, Atomic Energy Commission, told DH here. While Karnataka gets 27% of electricity from Kaiga 1&2 and 30% from Kaiga 3 and 4 the state would get almost 50% of electricity when the fifth and sixth units start generating power.India's all ongoing and planned nuclear projects are way behind schedule because of uncertainties associated with the new risk liability regime till last year as well as several manufacturing and manpower issues faced by major suppliers. To overcome the delays, the Department of Atomic Energy is set to approach the government seeking approval for 10 700 MWe reactors, which would be constructed in a “fleet mode”. This is expected to cut down on the time taken for approval and bring flexibility in fund allocation. The fifth and sixth nuclear power units at Kaiga are among these 10 reactors for which financial clearances would be sought. The others are two reactors in Haryana, two in Madhya Pradesh and four in Rajasthan, for which the land acquisition process has begun. The four 700 MWe under-construction reactors – two each in Kakrapar in Gujarat and Rawatbhatta in Rajasthan – are delayed by two years.
🔥The construction of the third unit at Kakrapar Atomic Power Plant began in November 2010 while KAPP-4 started in March 2011. Construction of Rajasthan Atomic Power Plant-7 & 8 began in 2011. Three of the four units are to be ready by June 2016, leaving only the RAPP-8 that was to be finished by December 2016. Basu now said KAPP-3 is likely to become operational only in 2018. Subsequently, there may be at least one functional new 700 MWe reactor every year. However, after several delays in finalising the schedule, the 500 MWe prototype fast breeder reactor at Kalpakkam might finally be commissioned later this year, he said"Operationalisation of the fast breeder reactor would mark India's entry into the second phase of its three-phase nuclear programme as envisaged by Homi Bhabha.
🔎CONCLUSION
The KAIGA NUCLEAR POWER PLANT has supplied a total electricity of 13.80 trillion Watts hour, has energy availability factor of 84.6%,operational factor of 91.3%,energy unavailability factor of 15.4% and finally the load factor of 87.3%.
No comments:
Post a Comment
If you have any doubts or clarification you need in my blog topics, I would 💯 try to clear it in an efficient manner as possible. I will also accept your suggestions.